Which task would actually shorten this run?
Select a task and change its duration. See when the other branch sets the pace.
Parallel retrieval run
Change duration
- Original task duration
- Longest path avoiding this task
- Maximum possible run saving
Run completion time
Each task starts when its dependencies finish. The model holds all other durations fixed and assumes enough workers to run both branches concurrently.
Reproduce this edit in Python
Rank tasks in your own run
Open a workflow JSON file to find its completion time and the ten tasks with the largest potential savings. Processing stays in this browser.
File format and limits
{"durations":{"plan":10,"search":80,"fetch":40,"merge":10},
"edges":[["plan","search"],["plan","fetch"],["search","merge"],["fetch","merge"]]}
Each edge is a prerequisite followed by its dependent task. Use nonnegative integer durations in one unit throughout. The file limit is 512 KiB, with up to 512 tasks and 4,096 edges. Each path must fit JavaScript’s safe integer range. The Python package accepts larger runs.
| Task | Duration | Run if zero | Saving |
|---|
Each row sets one task’s duration to zero and holds the others fixed. Savings are measured in the file’s time unit and cannot generally be added together.