Download tasks/fixture-loading/environment/world/REQUEST.md from reactive-labs/workcell-manipulation: direct link, hf CLI and curl.
- Browser
- Download file 2.95 kB
-
https://huggingface.co/datasets/reactive-labs/workcell-manipulation/resolve/main/tasks/fixture-loading/environment/world/REQUEST.md
- Command line
-
hf download hf://datasets/reactive-labs/workcell-manipulation/tasks/fixture-loading/environment/world/REQUEST.md
-
curl -L -o REQUEST.md https://huggingface.co/datasets/reactive-labs/workcell-manipulation/resolve/main/tasks/fixture-loading/environment/world/REQUEST.md
From: Test engineering lead, Larkfield Electronics (Unit 7, board test bay) To: Automation team, Corrie Bench Systems Subject: FT-2 fixture: loading controller for the SO-101
Hi,
The FT-2 bench fixture is wired and the SO-101 is bolted down next to it, but we still load every board by hand. We want the arm to do the whole cycle so the bay can run unattended for the night shift. Please write the controller.
One cycle:
- A board under test sits on the two locating pins of the fixture nest. The nest gets moved and turned a little every time someone services the bay, so take its pose from the overhead camera each cycle.
- Two cables come out of the cable duct at the back: a DC barrel plug (5.5 mm) for power and a 2-pin keyed header for the test signals. The barrel plug lies loose on the bench in front of the duct. The header plug sits in its parking socket on the right-hand side of the bench.
- The arm plugs the barrel plug into the board's DC jack (it goes in sideways, along the jack axis) and the header plug into the shroud on the board, key rib to the slot. The header latches with a click when it is fully home. The DC jack has no latch; its spring contact holds it.
- Then it presses the green TEST button on the nest. The fixture runs the test (one to three seconds) and lights the pass or fail lamp. Both lamps and the power and probe signals are on the fixture I/O.
- After a pass, the arm unplugs both connectors, sets both plugs down on the bench clear of the nest, lets go, and goes home. The header latch has to be pressed to release the header; pulling a latched header breaks the latch.
What must not happen:
- Boards lifted off their pins. If a board comes up off the pins it has to be re-seated by hand and the test is void. Unplugging is where this usually happens.
- Bent jacks and cracked shrouds. Any sideways load on a connector while it is engaged bends the contacts. Pushing too hard on the way in does the same. Our limits are in the acceptance sheet.
- Crushed plug housings. They are thin nylon.
- Slow cycles. The bay is sized for 100 s a board.
Things change from board lot to board lot and from cable to cable: the fit of the jack and the shroud (between 0.3 and 1 mm of clearance), which revision of the board it is (the header sits in a different place on revisions A, B and C, and engineering samples can have it anywhere along that edge), and how stiff the cables are.
The arm's mount has never been levelled properly. There are three touch-off probes on the bench for that: spring plungers with a switch, read on the I/O. Use them.
If the gripper or the camera fails during a cycle, the arm must stop and report which one failed. It must not carry on blind.
The acceptance sheet is ACCEPTANCE_TESTS.md and the fixture and cell data are in CELL_SHEET.md. Please don't
change the cell model or the acceptance files.
Thanks, Test engineering lead, Larkfield Electronics